HE Choeje Ayang Rinpoche

Avatar

Bodhgaya Project Update June 2008

Dear Dharma brothers and sisters,

The Bodhgaya project took off on March 8th, 2007 with the ground breaking ceremony performed by Rinpoche and ten monks. Right after the reinforcement of the raft foundation was completed and before we could start the casting, we had a heavy rainfall which filled the foundation with water and mud slides which can be seen in one of the pictures. It took us more than a week just to get the water and the soil out of the foundation before we could do the casting. This was the most toughest and challenging work in the melting heat of Bodhgaya but with our strong will and determination, we got all the soil cleaned and started the first casting on 21st of May, 2007.

We have planned a rain harvesting water tank with a capacity of 560,000 litres below the main temple which is why the foundation work has taken longer. We are finished with the casting of 30 inches raft foundation of approximately 12,000 sq ft and 6 ft casting of the outer, inner and baffle walls of the water tank. We are presently doing the bar bending of the tie beam on both the inner, outer and the baffle walls. I will continue to post more pictures as we keep progressing with the work.

With very warm regards and best wishes from Bodhgaya!

Truelha

23 ft wide and 30 inches ht raft fdn.JPG
 

inside 3 ft shuttering 1.JPG

Bodhgaya project photo update

The following are the most current photos of the Bodhgaya project site.

Front view – January 2008

bg 26 jan 08 front.JPG
 

Rear view – January 2008

bg 26jan08 back.JPG

Bodhgaya project 3D perspective

The following are the most current 3D perspectives of the Bodhgaya project made for us by the Architect.

Bodhgaya plan phowa

Bodhgaya plan phowa
 

Bodhgaya plan temple

Bodhgaya plan temple

Kathmandu and Bodhgaya update

Dear Dharma brothers and sisters,

I have just returned from Kathmandu after almost three weeks and am attaching some recent pictures to update you on the Amitabha Foundation project in Kathmandu and the Bodhgaya project.

The work is going very well. Cement carving is complete and painting has started in the main ground floor temple and the veranda. Flooring work in the veranda and exposed areas are continuing and wood work for doors and window shutters are progressing. Railings for the different floors are being welded and fitted. Civil work is almost complete except for some minor touch ups here and there.

The construction of the rain harvesting water tank will start soon and connecting roads will be created to start work on the retreat cottages.

I am returning to Bodhgaya on the 15th of December. The main temple is up to the plinth level and the floor slab will be caste after the water proofing work is complete.The footings are being caste for the foundation of the quarters.

Warm regards,

Truelha

Bodhgaya project photos

Dear Dharma brothers and sisters,

Some pictures to show you how the Bodhgaya project is progressing.

Best wishes and warm regards,

Truelha

Inside 3 ft wall casting

inside 3 ft wall casting.jpg

Inside 6 ft wall casting

inside 6ft wall casting.jpg

HE Choeje Ayang Rinpoche

Considered the world's living Phowa master – a lineage-holder of both the Nyingma and Drikung Phowa he continues the unbroken line of Drikung Phowa lamas from Buddha Vajradhara.



    Downlad Acrobat

    Some of our documants are in Adobe Acrobat format. You can download a free version of Adobe Acrobat Reader here